Why Flying Horse Powers Boulevard Bridges Are Being Built First

Crews got to Flying Horse Club Drive at 4 a.m. on the second Tuesday of October. By the end of that day they had finished a six-day job, setting 24 girders, each weighing 50 tons, on the pillars that will carry the new bridge deck. That's how KRDO described the milestone. Ridgeline Drive has been closed since early June. Flying Horse Club Drive has been down to one lane each way all summer and fall.

No part of Powers Boulevard has been built here yet. The bridges are going up first, and the order is on purpose. Living with a detour this winter is how Flying Horse avoids having a freeway job cut across its streets later.

A road that was drawn before the neighborhood was

According to the City of Colorado Springs project page, the concept design and alignment for extending Powers Boulevard from Highway 83 to Voyager Parkway were approved in 1997. That was before Flying Horse and Northgate were developed. Flying Horse was annexed into the city on Oct. 28, 2003, and the right of way for the future highway has been held open ever since.

Powers will be an expressway like the stretch between Research Parkway and Old Ranch Road. Its plans call for a new interchange at Highway 83, underpasses beneath Ridgeline Drive and Flying Horse Club Drive, and limited access points at Voyager Parkway and Highway 83. When the road is done, it will run 20 to 30 feet below where Flying Horse Club Drive sits today, according to the city's January open house boards.

Neighborhood traffic will cross over the expressway on bridges. The bridges have to exist before the trench below them can be dug.

The bridge north of here already shows the plan works

You can already drive over the first piece of this. Voyager Parkway closed in late 2023 so the Copper Ridge Metropolitan District could build a bridge that carries local traffic over the future Powers alignment. It reopened in 2024 and connects to the I-25/Powers Boulevard interchange at Exit 155, which was finished in 2021. Voyager had its disruption up front, and it's done.

Flying Horse is going through the same process now. The Gazette reported that the phasing is meant to reduce disruption during the later roadway work. In September, KRDO quoted Gayle Sturdivant, the city's deputy public works director, making the same point: building the bridges early means less disruption in the neighborhood once the roadway work starts.

Where each bridge stood in mid-October

Three bridges are under construction around the neighborhood. A fourth is still on paper.

Bridge What it carries Status as of mid-October 2026
Flying Horse Club Drive Two-way traffic over the future Powers 24 girders set over six days; the southbound bridge comes first, then the northbound
Ridgeline Drive A new two-lane bridge with sidewalks Girder placement scheduled to start the week after Oct. 13
Pedestrian bridge The golf-course crossing for walkers and golfers A temporary bypass is open now; a precast bridge comes next
Black Squirrel Creek Powers itself, on a high bridge over the creek Still in design

Black Squirrel Creek is the outlier. When Powers is finished, traffic will cross over that bridge and pass under the other three, KRDO reported. The three neighborhood bridges are the ones that keep your daily routes connected. The creek bridge belongs to the expressway.

What this winter looks like from the driver's seat

Things change through the winter, but the basic layout stays the same.

Ridgeline Drive stays closed. It's closed between Hawk Stone Drive and Veneto Way, and the city expects that to last for the whole bridge build at that spot. No reopening date has been announced. Girders at Ridgeline are the next big step, which is why the closure has to stay in place.

Flying Horse Club Drive stays open. The city says it will keep one lane in each direction for the life of the project. The lanes may shift from phase to phase, but the road won't close. The southbound bridge is being built first so two-way traffic can keep moving while the northbound bridge goes up. If you drive this road every day, plan on a new lane pattern at some point, but you won't lose the road.

The ground around the bridges is the winter job. The Gazette reported that earthwork to reshape the terrain near the bridges is scheduled for the winter months. The city's August update said retaining wall construction was expected to begin at Flying Horse Club Drive.

The hardest-hitting work has already wrapped. Pile driving at both bridge sites ran from June 29 to around July 15, during daytime hours. By August, the city reported that pile driving was finished and truck traffic was expected to drop in the next phase.

Your utilities should keep running. Lines are being relocated for the project, but the city doesn't expect service interruptions. If a short one is needed, residents are supposed to get advance notice.

The city hasn't put out a written turn-by-turn detour for Ridgeline. Instead, it points drivers to the posted signs and a detour map on its site.

The walk to the golf course gets a permanent crossing

If you walk or golf north of Flying Horse Club Drive, the crossing you're using now is temporary. Here's how Sturdivant explained it to KRDO:

"What you see today is just a temporary bypass, so pedestrians and golfers can use it. What we're going to be doing is coming in and putting a pre-cast pedestrian bridge in, just to the south of where that temporary crossing is today."

The city's open house boards describe this bridge as keeping the golf-course crossing in place. They also show the pedestrian path staying open during construction by way of a detour to the north. Like the road bridges, this one has to be in place before Powers is dug out below it. Otherwise the expressway would split that walking route in two.

The longer timeline, and how to keep up with it

Bridge construction is the 2026 phase. The city's timeline puts mainline roadway construction in 2027 through 2030. Officials told KRDO they hope to start the new Powers roadway next year, and Sturdivant told The Gazette the project is on track to be finished sometime in 2030. Final engineering is still underway. A traffic noise analysis is also in progress, and the city plans to share a summary of the findings with the community when it's done.

Sturdivant also explained why the city is building this, as The Gazette reported: "Right now in Colorado Springs, our main north-south route is solely I-25. This gives us the ability to have a secondary connection."

The newest construction email on the city's project page is dated Aug. 4, so the local news stations have had the fresher details this fall. To get news straight from the source:

When the city sends out a reopening date for Ridgeline, it should come through those alerts first.

If you're wondering how a multi-year road project might affect a move or sale in Flying Horse, I'm happy to talk it through with you, with no pressure and no rush. I keep up with these city updates for my Flying Horse clients and can share what I'm seeing. Sarah Barber is just a message away whenever you're ready. Let's Connect.

Work with Sarah

Whether you are a first-time buyer, a seasoned investor, or somewhere in between, Sarah brings the Colorado Springs, CO market knowledge and personal attention that make all the difference.

Follow Me on Instagram